The Department of Public Works is excited to be continuing the improvements of several water mains throughout town. Work began the week of March 22nd.
The project areas include the following streets:
- Bartlet Street
- Carmel Road
- Castle Heights Road
- Central Street
- Cheever Circle
- Chestnut Street
- Elm Street
- Joyce Terrace
- Judson Road
- Linwood Street
- Lockway Road
- Main Street
- Park Street
- Phillips Street
- Rock O Dundee Road
- Walnut Avenue
Update 5/04/2021: Due to weather conditions forecast over the next couple of days the scheduled shutdown for Tuesday, May 4th has been moved to Thursday, May 6th.
On Thursday, May 6th, the Town's contractor will continue water main work on Bartlet Street. This will include a shutdown on Bartlet Street, from Punchard Avenue to Chestnut Street (see map) from 8:30 am to 4:30 pm.
The construction may require some adjustments in neighborhood driving patterns; however, every effort will be made to minimize this inconvenience. There may be detours and delays. Local traffic and school buses will be allowed to access residences. Emergency vehicles will not be prevented from responding to calls.
There will be planned water main shutdowns, for which notices will be distributed to affected residents and businesses beforehand. We would like to thank you for your cooperation during these projects. For questions or concerns, please contact the Engineering Division at 978-623-8770 or dpw-engineering@andoverma.gov.