Posted on: May 4, 2022

[ARCHIVED] Water Main Replacements 2022

Water Main Work Status MapStarting May 5th, the Town of Andover’s general contractor will be replacing water mains on several streets around town (see map). Construction will occur Monday through Friday, from 7 am to 3 pm. We anticipate this construction to last approximately 5 months.

The streets included in the project are as follows: Poor St, Kensington St, Kenilworth St, Magnolia Ave, Ferndale Ave, Stirling St, Dumbarton St, Sutherland St, Carlisle St, Liberty St from Sutherland St to Carlisle St, Haverhill St from York St to Enmore St, North Main St from Railroad St to Joyce Ter, Pearson St, Essex St, and Ridge St. (see map)

The construction on North Main Street will take place during varied hours for 2-4 weeks starting on November 7th. Daytime work will take place from 7:00 AM to 3:00 PM and nighttime work will take place from 8:00 PM to 6:00 AM.

The construction may require some adjustments in neighborhood driving patterns; however, every effort will be made to minimize this inconvenience. There may be detours and delays. Emergency vehicles will not be prevented from responding to calls. There will be periodic shutdowns and potential discolored water associated with this water main work. Please report discolored water to the Water Division by email at MSDiscoloredWater@andoverma.us, or call 978-623-8707 and leave a message. View our Discolored Water PDF for more information and tips.

Feel free to contact the Engineering Division at 978-623-8770 with any questions or concerns.

Recent Notices

North Main St water shutdown Dec. 12th & 13th (Overnight): 
On the nights of Monday, December 12th, and Tuesday, December 13th, the Town's contractor will continue water main work on North Main St. This will include a water main shutdown of #161, 163, 165, 167, 168, 173, and 175 North Main Street (see map) from 10:00 pm to 5:00 am (OVERNIGHT). Construction will take place from 8:00 pm to 6:00 am. The construction may cause some adjustments in driving patterns; there may be detours and delays. Emergency vehicles will not be prevented from responding to their calls

The construction may cause some adjustments in driving patterns; there may be detours and delays. Emergency vehicles will not be prevented from responding to their calls. 

View Water Main Replacement Status Map

Facebook Twitter Email

Other News in Project News and Updates

Main Street island Replacement

Posted on: September 12, 2023

Water Main Replacements 2023

Posted on: April 13, 2023
Paving Season 2023

2023 Paving Season

Posted on: March 22, 2023